Reasonable objection
[edit] Introduction
A reasonable objection to a state of affairs is to object to or refuse to agree to carry out a particular task under instructions or an order – and having valid reasons for doing so. For example, a person may object to being ordered to fight for their country on the grounds of being a pacifist.
[edit] Construction
In construction, risks abound and, in many cases, it is the contractor who has to shoulder them. Typically, contractors face risks such as:
- Unknown or unknowable ground conditions.
- Delays not requiring an extension of time, e.g weather-related.
- Responsibilities for surveying previous work or existing structures.
- The construction process generally.
- Major variations.
- The work of consultants subcontractors and suppliers.
This is why some contracts and sub-contracts (such as JCT contracts) can, in certain circumstances, allow the contractor / subcontracator to raise an objection, such as to a variation order, if they have reasonable grounds.
A typical example might be where the client (employer) selects a sub-contractor with particular expertise, while leaving responsibility for their performance with the main contractor. Where the selected subcontractor was not pre-named in the contract (and is therefore now post-named) the contractor is able to raise reasonable objection within a certain time limit (often 7 days).
The grounds upon which a contractor may raise reasonable objection include:
- The specialist has a poor safety record.
- There are reasonable grounds for believing that the specialist may not be financially secure, solvent, reliable or technically competent.
- The tender sum is not believed to be financially viable.
- The programme is deemed to be unreasonable.
In the past, substantial variations that have changed the identity of the contract or even negated it completely have given contractors the right to reasonable objection, if an additional sum for the works could not be agreed on. However, this may no longer be as certain to succeed, thanks to a legal precedent from the 1990s.
In McAlpine Humberoak Limited v McDermott International, [1992] it was established that even in a situation where the extra works involved substantial changes, they did not necessarily alter or transform the identity of the contract. Therefore, the contractor (in this case for an offshore installation) was bound to the original contract and the objection overruled.
The 2016 JCT Standard Building Contract Without Quantities, clause 5.1.2, made clear that the right of reasonable objection relates to employers making changes to:
- Site access.
- Limitations on working space.
- Limitations on working hours.
- Changes to the specific order of the works.
Clause 5.1.1, made clear that the following allow a right of reasonable objection:
- Changes to the design, quality or quantity of the works.
- Changes to the kind or standard of materials or goods.
- Removal from the site of work or materials that are not defective.
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
Creativity, conservation and craft at Barley Studio. Book review.
The challenge as PFI agreements come to an end
How construction deals with inherit assets built under long-term contracts.
Skills plan for engineering and building services
Comprehensive industry report highlights persistent skills challenges across the sector.
Choosing the right design team for a D&B Contract
An architect explains the nature and needs of working within this common procurement route.
Statement from the Interim Chief Construction Advisor
Thouria Istephan; Architect and inquiry panel member outlines ongoing work, priorities and next steps.
The 2025 draft NPPF in brief with indicative responses
Local verses National and suitable verses sustainable: Consultation open for just over one week.
Increased vigilance on VAT Domestic Reverse Charge
HMRC bearing down with increasing force on construction consultant says.
Call for greater recognition of professional standards
Chartered bodies representing more than 1.5 million individuals have written to the UK Government.
Cutting carbon, cost and risk in estate management
Lessons from Cardiff Met’s “Halve the Half” initiative.
Inspiring the next generation to fulfil an electrified future
Technical Manager at ECA on the importance of engagement between industry and education.
Repairing historic stone and slate roofs
The need for a code of practice and technical advice note.
Environmental compliance; a checklist for 2026
Legislative changes, policy shifts, phased rollouts, and compliance updates to be aware of.